The Federal Government, weekend, expressed satisfaction over the progress of work done by the contractor handling the Lagos-Badagry expressway, which is funded by Nigerian National Petroleum Company, NNPC, under tax credit funding to the tune of N15 billion.
Director of Federal Highways in South West, Adedamola Kuti, who made this known during the inspection of Section 3 of the expressway, which begins from Agbara to Seme, to ascertain the level of work done, said the project, which is being supervised by the Federal Ministry of Works and Housing, is going as expected.
According to Kuti: “About 17 kilometers have been completed at various stretches on the Badagry bound lane, while measures are on to further speed up the pace of construction works on the remaining sections. So far, NNPC funds have brought in a lot of relief to this job. We have been able to pay some of the outstanding bills for certified works that have been done. So, we have our certificates No. 4 and 5 paid up by the NNPC.
“That is why you are seeing this tremendous progress that is ongoing on this road. NNPC funding for this job is just about 15 billion Naira but we have been assured that government will not stop funding,” he said.
Kuti who said that the project was about 25 percent completed, expressed hope that the government’s continued funding will get the project to about 80 percent completion within a year.
He pointed out that the contract was awarded in 2018 but due to funding constraints, actual construction began in earnest between 2020 and 2021 after the SUKUK funding came in, stressing that it was the NNPC Tax Credit Scheme that has fast-tracked the project to the present level.
“From December 2021 and this year 2022, this project has been placed under the Tax Credit initiative of the Federal Government that is being sponsored and being financed by the NNPC.
“We are here to see the progress that has been made so far on this road. This road is very sensitive to the federal government.
“Out of the 21 critical roads under NNPC funding, we have two in the South West and Lagos-Badagry Expressway happens to be one of them. From Agbara to Badagry is about 46 kilometers.”